Gautam Adani fails to keep September 1 date with Vizhinjam port

The delay is being attributed to a serious shortage of limestone required for building the breakwaters. Then there was Cyclone Ockhi which landed a huge beating in 2017 and took away 150 metres of the constructed breakwater

  • WhatsAppBookmarkBookmark
Listen to this article :
Gautam Adani

Gautam Adani

Private multi-port operator Gautam Adani failed to keep his September 1 promise of berthing the first ship from the Vizhinjam Port, near here, on Saturday. A tremendous ammount of work still remains.

Adani Vizhinjam Port Private Ltd (AVPPL) had on December 5, 2015 targeted September 1, 2018 to finish the first phase of the Kerala port. Adani had said it would be operational in 1,000 days, which was Saturday. The then Oommen Chandy government had inked the 2015 agreement for the international multi-purpose deepwater seaport project at a cost of Rs 7,525 crores. Adani Ports, which was the lone bidder had sought a Rs 1,635 crore grant for this.

Read Next Story
Rahul Gandhi suffers from schizophrenia, says union minister Ashwani Choubey›

Trending Stories

Latest Photoscta-pos

Latest VideosView All

Latest Web StoriesView All

Mid-Day FastView All