Mumbai will have to wait for extra water, thanks to PWD delay
Updated On: 09 July, 2013 01:09 AM IST | | Sujit Mahamulkar
Delay in completion of a bridge on Mokhada-Khodala road is depriving the city of an additional 455 million litres of water per day
Listen to this article :
A year after the much-awaited Middle Vaitarna dam project, which is expected to augment the city’s water supply by 455 million litres per day, was completed; it has hit another stumbling block -- an incomplete bridge on the Vaitarna River is delaying the commissioning of the project.

Mired in delays: In May, PWD officials had set a deadline of June 23 for completion of the bridge on Mokhada-Khodala road