Bullet train project: First steel bridge installed in Maharashtra after 1,300-km journey
Updated On: 29 September, 2026 12:39 PM IST | Thane | mid-day online correspondent
The bridge is the first steel structure of its kind to be set up in Maharashtra under the ambitious high-speed rail project. It was transported to Thane from a specialised workshop in Trichy, Tamil Nadu, located around 1,300 km away, and assembled at the site before being launched into position

The first steel bridge for the Mumbai-Ahmedabad bullet train project is installed over NH-3 at Dive-Anjur in Thane. Representational pic
A 100-metre-long steel bridge weighing 1,405 metric tonnes has been installed in Maharashtra’s Thane district as part of the Mumbai-Ahmedabad bullet train project, officials said.
The bridge is the first steel structure of its kind to be set up in Maharashtra under the ambitious high-speed rail project. It was transported to Thane from a specialised workshop in Trichy, Tamil Nadu, located around 1,300 km away, and assembled at the site before being launched into position.