A total workforce of 60 personnel participated in the operation, including 20 railway staff members and 40 contractor personnel, Western Railway said in an official statement
Listen to this article :

The Western Railway carried out the work during a three-hour traffic and power block covering all railway lines. Pic/Special Arrangement
Western Railway on Sunday said that it has completed a major phase of construction for a new 12-metre-wide Foot Over Bridge (FOB) at Marine Lines station.
A total of 19 steel girders, each measuring 20 metres in length and weighing a combined 95 metric tonnes, were successfully launched at the station, officials said.