The BMC opened one arm of the bridge on June 1, and was expecting to open the second one by the end of July. But, officials are finding it difficult to meet this target due to rains. “We had set this deadline because we thought we would get a long dry spell in June,” said an official
The BMC plans to install the girder for the second arm of the Delisle Road bridge on June 20. “The girder will be launched on two spans of the BMC’s approach road, followed by shuttering and reinforcement work. A long dry spell is not required to launch a girder,” the official added
The last phase in the project was concreting work, which cannot be done during a wet spell, the official said, adding that initially, the plan was to complete this work in the first week of July
The first deadline for completion of the R138-crore project was May 2022, but it was extended to December 2023 and then May 2023. It was partially opened on June 1