BMC Commissioner Ashwini Bhide reviewed the tunnel work on Monday and directed officials to maintain construction speed while prioritising safety and quality. Pics/BMC
According to the BMC, the necessary procedures for beginning excavation of the second tunnel are nearing completion
The civic body also said that a 1.26-km flyover connecting Dindoshi Court to Dadasaheb Phalke Film City has been completed under Phase 3 of the project
The Brihanmumbai Municipal Corporation (BMC) has also completed the site acceptance test (SAT) for the second tunnel boring machine, Vihar, paving the way for excavation of the second tunnel
The twin-tunnel section of the GMLR project will connect Dadasaheb Phalke Film City in Goregaon East with Amar Nagar in Mulund West, passing beneath Sanjay Gandhi National Park, the statement said
The project involves two parallel tunnels, each around 5.30 km long and designed with three lanes
The first tunnel boring machine, Tulsi, became operational on August 17, 2026. Since then, it has completed 183 metres of excavation at an average rate of 5.5 metres per day, according to the BMC
Construction of 87 permanent ring segments, which form an important part of the tunnel structure, has also been completed. In addition, six temporary ring segments have been installed
During her site visit, Bhide reviewed the excavation process, project progress, machinery performance, construction quality and safety arrangements
The two machines will be used to construct the parallel tunnels beneath the national park, forming a key part of the east-west road link between Goregaon and Mulund
Separately, the BMC has completed a 1.26-km flyover connecting Dindoshi Court to Dadasaheb Phalke Film City in Goregaon under Phase 3 of the GMLR project