16 October,2026 12:02 PM IST | Mumbai | Vinod Kumar Menon
While the uptick in recoveries offers hope to homebuyers awaiting compensation, the key question remains: how quickly will these orders translate into money in their bank accounts? Representation Pic/iStock
For homebuyers who have spent years chasing developers for delayed flats, a favourable ruling should end the struggle. But winning the case is only half the battle; getting the compensation is another.
Since its establishment in May 2017, MahaRERA has recovered R369.45 crore against compensation orders worth Rs 1037.86 crore, a recovery rate of about 45 per cent, leaving much still unpaid. Collections have accelerated, with around Rs 260 crore recovered between May 2017 and December 2025, followed by another Rs110 crore in 2026.
While the uptick offers hope to homebuyers awaiting compensation, the key question remains: how quickly will these orders translate into money in their bank accounts?
The state has set up a new procedure to speed up recovery of MahaRERA compensation orders. Resident deputy collectors and additional district collectors in every district are now designated revenue recovery officers for MahaRERA cases, explained a MahaRERA official. The move addresses a gap in the process: MahaRERA decides complaints and orders developers to pay compensation, but the money is actually recovered by revenue authorities.
Under Section 40(1) of the RERA Act, 2016, if a developer fails to comply within the stipulated period, MahaRERA issues a recovery warrant and sends it to the district collectorate. Revenue officials then proceed under the Maharashtra Land Revenue Code, 1966.
Dedicated officers, the government hopes, will improve coordination and cut delays in executing warrants.
Mumbai Suburban leads the state in compensation recovery, collecting Rs 142.31 crore against orders worth R415.93 crore. Mumbai City follows with Rs 85.80 crore of Rs 231.81 crore, and Pune with Rs 68.63 crore of Rs 230.45 crore.
Thane City has recovered Rs 36.79 crore of Rs 87.45 crore, while Alibaug has collected Rs 12 crore of Rs 27.54 crore.
These five jurisdictions account for most of the recovery. But the gap between what was ordered and what was collected shows large dues remain outstanding in the major urban markets, where homebuyers have fought long disputes with developers.
The five jurisdictions together account for Rs 345.53 crore of the Rs 369.45 crore recovered statewide. The remaining Rs 23.92 crore has been recovered across other districts.
District-wise compensation recovery
|
District |
Compensation ordered in crores |
Amount recovered in crores |
Balance yet to be recovered in crores |
|
Mumbai Suburban |
Rs 415.93 |
Rs 142.31 |
Rs 273.62 |
|
Mumbai City |
Rs 231.81 |
Rs 85.80 |
Rs 146.01 |
|
Pune |
Rs 230.45 |
Rs 68.63 |
Rs 161.82 |
|
Thane City |
Rs 87.45 |
Rs 36.79 |
Rs 50.66 |
|
Alibaug |
Rs 27.54 crore |
Rs 12.00 |
Rs 15.54 |
|
Total for these five jurisdictions |
Rs 993.18 |
Rs 345.53 |
Rs 647.65 |
MahaRERA has also reported that seven districts - Nagpur, Palghar, Nashik, Chhatrapati Sambhajinagar, Sindhudurg, Solapur and Chandrapur - have brought their outstanding compensation amounts down to zero. Together, they recovered R23.92 crore, which accounts for the gap between statewide recovery and the five major jurisdictions' collections. Their zero-outstanding status means the pending compensation there has been cleared. It does not show how long buyers waited to be paid, explained a MahaRERA official.
Legal hurdles are blocking recovery of a large part of the compensation. Rs 104.70 crore is stuck before the National Company Law Tribunal, and another Rs 104.46 crore falls under the MPID Act, 1999. In all, Rs 209.16 crore in compensation cannot currently move through regular recovery.
|
Total compensation covered by recovery orders |
Rs 1037.86 crore |
|
Total compensation recovered |
Rs 369.45 crore |
|
Difference between orders and recovery |
Rs 668.41 crore |
|
Cases pending before NCLT |
Rs 104.70 crore |
|
Cases covered by the MPID Act |
Rs 104.46 crore |
|
Total involving these legal restrictions |
Rs 209.16 crore |
MahaRERA says its recovery rate of about 45 per cent is the highest among India's RERA authorities. The figure measures money collected against the value of recovery orders, not the share of buyers paid.
The drive is gaining pace, with Rs 110 crore collected in 2026 so far, and dedicated recovery officers are meant to sustain it.
But for buyers who have spent years paying EMIs, rent and legal fees, the real test is how much of the award has reached them, and how soon. That gap remains wide.
âRERA law is not a standalone law ie it does not operate in isolation. The real estate sector requires involvement of lenders and mortgage of property, because liquidity and capital play a key role. Hence, apart from the flat purchasers, there may be more factors and stakeholders which can determine the actual outcome of recovery of money by execution of the decree'
Advocate Akash Menon says, âWhile the report may paint an optimistic picture, the on-ground realities we see in metropolitan regions like Mumbai and Pune remain grim. A predominant cause for less-than-ideal recoveries remains the lack of transparency and accountability in the execution of RERA orders.
The onus of execution by law remains with the government executive, typically the office of the district collector. While, as of recently, there are nodal officers who are seemingly assigned exclusively with the tasks of execution of RERA orders, an improved statutory ecosystem with more aggressive recovery processes and better transparency of execution statuses is the need of the hour. Public faith in the system will be restored if the law can bridge these systemic flaws.'