shot-button
Union Budget Union Budget
Home > Mumbai > Mumbai News > Article > Mumbais JJ Hospital building project misses third deadline handover delayed again

Mumbai's JJ Hospital building project misses third deadline, handover delayed again

Updated on: 02 January,2026 08:03 AM IST  |  Mumbai
Ritika Gondhalekar | ritika.gondhalekar@mid-day.com

Healthcare facility’s dean says there has been no communication from firm concerned regarding handover of structure

Mumbai's JJ Hospital building project misses third deadline, handover delayed again

The under-construction building next to JJ Hospital on December 31. PIC/SHADAB KHAN

Listen to this article
Mumbai's JJ Hospital building project misses third deadline, handover delayed again
x
00:00

The long-delayed building project at Sir JJ Hospital has missed yet another deadline, raising serious concerns over accountability and patient infrastructure in one of Mumbai’s largest public healthcare facilities. The contractor tasked with constructing the new hospital building was expected to complete and hand over the fully constructed structure by December 2025. However, as of now, neither has the handover taken place nor has the contractor formally applied for an extension.

Dr Ajay Bhadarwar, dean of the hospital, said, “We have not received any communication from the contractor regarding the completion or handover of the project. There has been no official handover of the building to date. We are still waiting for clarity on when the work will be completed.”


Officials from the public works department (PWD) also confirmed that no request for an extension of time had been submitted by the contractor. “As per our records, the contractor has neither completed the project within the stipulated time nor sought a formal extension. This is a clear violation of contractual timelines. Our seniors have conducted meetings with him, and a meeting is scheduled next week,” said Shashi Jamdar, junior engineer from the PWD. 



While the contractor had asked for an extension till next March, the PWD department asked the company to finish work by November this year and hand over the building to the hospital by December at the latest. The repeated delays have sparked concern among the medical community. “If these delays hadn’t happened, some load would have been reduced from the already-stretched public healthcare system,” said health activist Dr Jamila Shaikh.

Delay timeline

July 21, 202: Original contract duration 36 months from when the project began

July 20, 2023: Original date of project completion

March 30, 2025: A 20-month extension was given as only 29 per cent of the work had been completed. This ended on

December 2025: The contractor asked for another extension till March 2026. But PWD directed it to complete the work and hand over the new building to the hospital administration

"Exciting news! Mid-day is now on WhatsApp Channels Subscribe today by clicking the link and stay updated with the latest news!" Click here!

Did you find this article helpful?

Yes
No

Help us improve further by providing more detailed feedback and stand a chance to win a 3-month e-paper subscription! Click Here

Note: Winners will be selected via a lucky draw.

Help us improve further by providing more detailed feedback and stand a chance to win a 3-month e-paper subscription! Click Here

Note: Winners will be selected via a lucky draw.

jj hospital infrastructure development Infrastructure health mumbai news mumbai

Mid-Day Web Stories

Mid-Day Web Stories

This website uses cookie or similar technologies, to enhance your browsing experience and provide personalised recommendations. By continuing to use our website, you agree to our Privacy Policy and Cookie Policy. OK