Residents question delay as Bandra Talao makeover shows no visible progress

Updated on: 20 March,2026 08:46 AM IST  |  Mumbai
Madhulika Ram Kavattur | mailbag@mid-day.com

Rs 15 crore revival begins on paper, but the Bandra Talao rejuvenation project remains stalled on site, with only metal beams erected and no visible work, prompting BMC to issue a show-cause notice to the contractor

Residents question delay as Bandra Talao makeover shows no visible progress

Bandra Talao seen in a deteriorated condition, with polluted water and poor upkeep, on Thursday. Pics/Satej Shinde

Listen to this article
Residents question delay as Bandra Talao makeover shows no visible progress
x
00:00

Nearly a month after work on the long-awaited rejuvenation of Bandra Talao (Swami Vivekanand Sarovar) was officially flagged off, the ground tells a different story. Despite a December  tender and a January 12 start date, the iconic waterbody near Bandra station remains untouched, with only metal beams erected around the lake but no visible activity on site, prompting residents to question whether the project has stalled before it even began.

A woman walks over broken tiles along the Bandra Talao promenade on Thursday
A woman walks over broken tiles along the Bandra Talao promenade on Thursday


Project snapshot
Project cost: Rs 15.13 crore



Start date (on paper)
January 12, 2026

Contract period 18 months
(excluding monsoon)

Metal beams erected around the Bandra Talao, but no visible rejuvenation work of the lake has begun on site Metal beams erected around the Bandra Talao, but no visible rejuvenation work of the lake has begun on site

Contractor
WTE Infra Projects Pvt Ltd

Delay decoded
Delay so far 2 months

Action taken
Show-cause notice issued by BMC

Penalty

Proposed against the contractor
“There has been a delay of about two months. We have issued a show-cause notice and proposed a penalty,”
- Dinesh Pallewad, H West ward officer

Damaged railings around Bandra Talao (captured on Thursday) highlight the need for urgent restoration
Damaged railings around Bandra Talao (captured on Thursday) highlight the need for urgent restoration

What’s planned?

>> Possible floating gardens
>> Promenade restoration
>> Overall beautification of the Talao precinct

What the project aims to fix?

>> Removal of aquatic weeds
>> Reduction of pollutants

Key approvals underway include

>> Dumping and disposal of silt and solid waste
>> Clearances from road and civic authorities
>> Planning execution to avoid public disruption.

“As this is a sensitive and heritage project, we are taking utmost precaution,”
Rohit Patankar

Why no work is visible

The contractor maintains that groundwork is underway, just not on-site.

“We are currently in the stage of taking permissions from all relevant authorities… physical work will begin only after all clearances are in place,”
Rohit Patankar, engineer, WTE Infra Projects

"Exciting news! Mid-day is now on WhatsApp Channels Subscribe today by clicking the link and stay updated with the latest news!" Click here!

Did you find this article helpful?

Yes
No

Help us improve further by providing more detailed feedback and stand a chance to win a 3-month e-paper subscription! Click Here

Note: Winners will be selected via a lucky draw.

Help us improve further by providing more detailed feedback and stand a chance to win a 3-month e-paper subscription! Click Here

Note: Winners will be selected via a lucky draw.

Bandra water crisis Water cut Mumbai water brihanmumbai municipal corporation mumbai news mumbai

Mid-Day Web Stories

Mid-Day Web Stories

This website uses cookie or similar technologies, to enhance your browsing experience and provide personalised recommendations. By continuing to use our website, you agree to our Privacy Policy and Cookie Policy. OK