26 March,2025 08:36 AM IST | Mumbai | A Correspondent
Civic chief Bhushan Gagrani holds meeting at BMC HQ, on Tuesday
As the completion date to concretise over 420 km of roads in the city nears, Brihanmumbai Municipal Corporation (BMC) chief Bhushan Gagrani on Tuesday held a high-level meeting with the civic officials and directed them to work as per micro-planning and set a specific completion date for each road project.
The concreting of the roads needs to be completed in the next 70 days by May 31, 2025. He said that the officials from the water engineering, stormwater drainage, sewerage departments, and various utility authorities should coordinate to ensure smooth execution of the projects.
Gagrani also directed senior engineers to conduct surprise site visits to monitor progress and the quality at sites as well as the concrete plants. They should actively participate rather than just being present in a technical capacity, he said, while ordering a strict prohibition on digging new concrete roads.
"Complaints from public representatives and citizens, such as lack of barricades, scattered debris, and cement-laden water in stormwater drains, were addressed with specific remedial measures," Gagrani said while addressing the official.
ALSO READ
Mumbaikars swap morning walks for evening strolls as air quality dips
Mumbai: Jain community protests demolition of 35-year-old temple in Vile Parle
Affordable treatment at revamped Bhagwati Hospital under Ayushman Bharat: Goyal
Carnac Bridge work in final phase, completion by June 10: BMC official
BMC officer transferred after Jain temple demolition in Mumbai
Engineers reported that delays in road work were caused by underground utility lines from the water engineering, sewerage, and other utility agencies. To resolve this, a fixed timeframe for these departments to complete their work was decided, ensuring uninterrupted roadwork.
Abhijit Bangar, additional municipal commissioner, who was also present in the meeting, told officials that completed roads must have thermoplastic markings, zebra crossings, cat eyes, and yellow thermoplastic grid markings at intersections to enhance usability and aesthetics.
Bangar further said that 701 km of roads are part of the project. "If roads are not concreted before the monsoon, contractors will be responsible for pothole repair. Contractors must arrange mastic cookers and manpower in advance to ensure potholes are filled before the monsoon", said Bangar.