15 April,2026 07:53 AM IST | Mumbai | Rajendra B. Aklekar
File pic
Work on two key Metro corridors linking Mumbai's western and eastern suburbs via Bandra-Kurla Complex (BKC) and the airport has been accelerated, with the Mumbai Metropolitan Region Development Authority (MMRDA) pushing parallel progress on track installation and station systems, even as civil structures are still being completed. The move is aimed at cutting execution timelines and avoiding last-mile delays on Metro Lines 2B and 7A, both of which are critical for cross-city connectivity and airport access.
>> Corridors: Metro Line 2B (Yellow), Metro Line 7A (Red)
>> Key link: BKC, airport connectivity
>> Work focus: Track laying, station systems, signage
>> Target: Faster execution, reduced last-mile delays
Contract CA-286 covers
>> Design, supply, installation, testing and commissioning of ballastless tracks
>> Applicable to Line 2B (elevated) and Line 7A (underground)
Planned between IL&FS and MTNL stations Purpose:
>> Better train management
>> Reduced congestion during peak hours
Parallel execution strategy
>> Track work and station systems being executed simultaneously
>> Aim is to align completion timelines with pending civil works
>> Focus on avoiding delays after viaduct readiness
>> Ballastless tracks for durability and low maintenance
>> Four crossovers for operational flexibility
>> Design speed: up to 95 kmph
>> 25 kV AC overhead electrification
>> CBTC-based signalling for automated operations
Metro Line 2B (Yellow) DN Nagar to Mandale
>> Length: ~23.5 km (elevated)
>> Connects: Andheri, Bandra, BKC, Kurla, Chembur, Mankhurd
>> Interchanges with:
Line 1 (Blue)
Line 3 (Aqua)
Line 7 (Red)
Line 4 (Green)
>> Role: Major east-west connector across congested stretches
>> Length: 2.138 km
>> Mix of elevated and underground sections
>> Connects Western Express Highway corridor to the airport
>> Interchange with Aqua Line 3 at the airport
>> Design speed: 95 kmph (operational ~80 kmph)
Contract CA-306 floated for 13 elevated stations on Line 2B
Stations include:
>> ESIC Nagar, Prem Nagar, Indira Nagar
>> Nanavati Hospital, Khira Nagar, Saraswat Nagar
>> Bandra, ITO, IL&FS, MTNL
>> SG Barve Marg, Kurla East, Eastern Express Highway
>> Standardised colour-coded signage
>> Illuminated high-visibility boards
>> Glow-in-the-dark emergency markers
>> Braille-enabled navigation
>> Weather-resistant materials for long-term use
Jaideep Kane, Infra enthusiast
âI think they are expanding Line 2B to Chembur, and it will be very useful when the Monorail starts operating. And for 7A, it is a perfect airport connection for all'
Arindam Mahapatra, Commuter
âWith the tenders out for track laying at this stage, MMRDA should plan accordingly about completing the girder launching in the remaining areas at Kurla and BKC so that by the time girder launching is completed, track installation can start immediately and provide some relief to office goers heading to BKC'
Yash Mhadgut, Infra enthusiast
âIt's great that tracks are being laid for Line 7A and Line 2B, as both lines are crucial for interchanges. Line 7A will allow direct transfer from Red Line to Aqua Line, and Line 2B will connect the western suburbs, BKC and the eastern suburbs directly. Navi Mumbai connection will become easier via Line 2B through Mankhurd station'