Mumbai's Jogeshwari Junction set to handle long-distance trains from January 2027

16 July,2026 08:15 AM IST |  Mumbai  |  Rajendra B. Aklekar

Long-distance trains are expected to begin operating from Mumbai`s upcoming Jogeshwari Junction from January 2027. Western Railway also plans to develop the station into a multimodal transport hub, with a hotel and shopping mall proposed in the second phase, subject to technical and financial feasibility.

The meeting was attended by senior WR officials, local public representatives, and civic leaders. PICs/BY SPECIAL ARRANGEMENT


Your browser doesn’t support HTML5 audio

Long-distance trains are expected to originate from the upcoming Jogeshwari Junction from January 2027, while the station is also being planned as a modern multimodal transport hub with the possibility of a hotel and shopping mall in its second phase, subject to technical and financial feasibility.

The assurance was given by Western Railway (WR) General Manager Ramashray Pandey during a meeting with Mumbai North West MP Ravindra Waikar to review pending railway projects and commuter issues in the constituency.


Work on the upcoming Jogeshwari Junction underway

The meeting was attended by senior WR officials, including DGM (General) Ujjwal Dev and Secretary Sachin Sharma, along with local public representatives and civic leaders. Pandey also assured the MP that a joint inspection of Andheri and Jogeshwari stations would be scheduled with railway officials once a date is finalised.

Seamless connectivity

The proposed Jogeshwari Junction is being developed to provide seamless connectivity between suburban rail, long-distance trains, Metro and other modes of transport. The project will also include parking facilities for both cars and two-wheelers.

Key discussions…

Long-distance trains: The station is expected to start handling outstation trains from January 2027

Harbour line extension: The 7.08-km Goregaon-Borivli Harbour Line extension, estimated to cost R898.29 crore, targeted for completion by March 2029

15-car infrastructure: Platform extension work at Andheri has been completed, enabling 15-car local train operations; work to lengthen platforms on slow corridor between Bandra-Andheri underway

Multimodal hub: Besides railway infrastructure, Jogeshwari station is proposed to be developed as a modern multimodal transit hub integrating rail, Metro and other transport systems; if technically and financially viable, hotel and shopping mall may be added

Andheri station upgrades: Additional lift under construction expected to become operational by October 2026; approval granted for two more escalators, with completion targeted by June 2027

Jogeshwari escalators: Approval granted for installation of one additional escalator at Jogeshwari station, with completion expected by June 2027

Subhash Nagar FOB: Escalator for Subhash Nagar foot overbridge sanctioned; scheduled for completion by June 2027

Passenger amenities: MPLADS (Member of Parliament Local Area Development Scheme) funds offered for construction of toilets, waiting rooms, and breastfeeding rooms at stations in Mumbai North West constituency

RPF manpower shortage: Railway officials informed that while 1894 RPF personnel are required for stations in the area, only 1409 are currently deployed, leaving 485 vacancies

Railway helpline: Officials said the existing 139 railway helpline continues to handle passenger complaints across the country

Ambulance services: Ambulances are currently stationed at Andheri and Goregaon railway stations in coordination with the state government, while a similar facility is being considered for Jogeshwari

[popcorn number="Rs 898.29 cr" desc="Estimated cost of Goregaon-Borivli Harbour Line extension" class="Default"]