Mumbai Elevated Eastern Freeway Extension: MMRDA begins precast segment erection

30 September,2026 07:14 AM IST |  Mumbai  |  Ranjeet Jadhav

MMRDA begins erecting 90-tonne-plus precast segments for 13.9-km elevated corridor; first segment launched near Bhandup Pumping Station

Ongoing work on the Elevated Eastern Freeway Extension. Pics/By Special Arrangement


Your browser doesn’t support HTML5 audio

The Elevated Eastern Freeway Extension has entered a key construction phase, with the Mumbai Metropolitan Region Development Authority (MMRDA) beginning to erect precast segments above the busy Eastern Express Highway while traffic continues to move below. The first segment, weighing more than 90 tonnes, was launched at Pier P78 near Bhandup Pumping Station on Monday using a 115-metre-long mechanised Launching Gantry-01 (LG-01).

The operation marks the shift from foundation and pier construction to the erection of the elevated corridor's superstructure. The mechanised gantry allows the heavy segments to be lifted and positioned above the live traffic corridor with limited ground-level support.

The project in numbers

13.9 km
Length of elevated corridor

6 lanes
3+3 lane configuration

Rs 2682 crore
Accepted contract amount

40 m
Typical span length

115 m
Length of Launching Gantry-01

106 tonnes
Maximum segment weight

1450 tonnes
Maximum span weight

How the segments will eventually become a freeway

The precast segments will be erected span by span and longitudinally post-tensioned to form the elevated structure

Cast
Precast segments are manufactured at the project casting yard

Lift
The launching gantry picks up the heavy segments

Position
Segments are placed between completed piers above the existing road

Post-tension
The segments are longitudinally post-tensioned to form complete spans

Repeat
The gantry advances along the corridor as construction progresses

What happens next?

According to MMRDA, LG-01 will progressively erect segments towards Mumbai. A second gantry, LG-02, will advance from Vikhroli towards Mumbai, while the Ground Support System will progress between Bhandup and Kanjurmarg towards Thane.

"LG-01 will progressively erect 1632 precast segments towards Mumbai, which will be longitudinally post-tensioned to form complete bridge spans. A second gantry (LG-02) will advance from Vikhroli towards Mumbai, while the Ground Support System (GSS) will progress between Bhandup and Kanjurmarg towards Thane," said MMRDA on X.

Work so far

81% monopiles completed

19% group piles completed

51% piers completed

33% pier caps completed

135 precast segments cast, according to MMRDA

The project uses 2500-mm-diameter monopiles and a single-pier arrangement designed to reduce the construction footprint while allowing work to continue above the live traffic corridor.

Where will it run?

The elevated corridor will run from Chedda Nagar on the Eastern Express Highway to Anand Nagar near Thane, passing through the eastern suburbs.

Four planned entry/exit points:
. Chedda Nagar
. Kanjurmarg
. Airoli Bridge
. Mulund Octroi Naka

What the project is expected to do

Once completed, the corridor is expected to ease pressure on the Eastern Express Highway and improve connectivity between South Mumbai and Thane. MMRDA expects the journey between South Mumbai and Thane to take around 20-25 minutes. Earlier MMRDA material has put the expected travel time at around 25-30 minutes, so the final figure should be treated as an estimate.