Mumbai Metro-3 will not meet 2023 deadline

Mumbai Metro-3 will not meet 2023 deadline

Officials say only 93 per cent work between Aarey and BKC complete, trials and safety certifications will cause further delay

25 November,2023 07:18 AM IST | Mumbai | Rajendra B. Aklekar
Mumbai Metro Blue Line 1 achieves highest ridership post-Covid-19

Mumbai Metro Blue Line 1 achieves highest ridership post-Covid-19

The Mumbai Metro Blue Line One on Wednesday announced that last week it achieved the highest single-day ridership of 479,333 passengers on 27 September, surpassing the pre-Covid-9 ridership, setting a new record.

04 October,2023 03:58 PM IST | Mumbai | Rajendra B. Aklekar
Mumbai: Blasting at Metro site damages vehicles and windows at Mantralaya

Mumbai: Blasting at Metro site damages vehicles and windows at Mantralaya

Controlled blasting work at Aqua Line 3 sends stones and dust flying, MMRCL halts operation, begins review of construction work after which corrective action will be taken

01 September,2023 07:30 AM IST | Mumbai | A Correspondent
Mumbai: Environmentalists smell a scam in tree transplantation

Mumbai: Environmentalists smell a scam in tree transplantation

Say MMRCL is killing trees in name of transplantation, as 65 per cent of the trees replanted by it in 2020 have died

06 July,2023 07:06 AM IST | Mumbai | Ranjeet Jadhav
Mumbai: Rs 3.81 crore spent only on Metro 3 litigation

Mumbai: Rs 3.81 crore spent only on Metro 3 litigation

Delays due to controversies have escalated the underground line’s cost by Rs 14,000 cr

29 March,2023 05:46 AM IST | Mumbai | A Correspondent
Mumbai: Litigations delaying Metro car shed project, MMRCL tells Bombay HC

Mumbai: Litigations delaying Metro car shed project, MMRCL tells Bombay HC

MMRCL, a nodal agency, told the HC that due to the court cases, it could not cut down trees in 2019 and this has now led to an increase in the number of trees that are required to be cut for the project at suburban Goregaon

16 February,2023 03:28 PM IST | Mumbai | PTI
MMRCL to launch first phase of Metro-3 corridor in 2023

MMRCL to launch first phase of Metro-3 corridor in 2023

In a release, the MMRCL said it received all eight coaches of the metro train, manufactured in the Alstom Plant in Sri City of Andhra Pradesh on Thursday, and these will undergo mandatory tests on a 5-km stretch between the ramp at Sariput Nagar and Sahar

30 December,2022 09:34 PM IST | Mumbai | PTI
Mumbai: Second Aqua Line 3 train to arrive in city soon

Mumbai: Second Aqua Line 3 train to arrive in city soon

MMRCL wants to begin phase 1 operations between Aarey and Bandra Kurla Complex by June 2023

01 December,2022 07:07 AM IST | Mumbai | Rajendra B. Aklekar
Strictly abide by undertaking that no trees would be cut in Aarey colony: SC

Strictly abide by undertaking that no trees would be cut in Aarey colony: SC

The top court had restrained the authorities from cutting any more trees in the Aarey colony after the solicitor general had submitted on behalf of the state of Maharashtra that no further trees will be cut.

24 August,2022 01:24 PM IST | New Delhi | PTI
No tree cutting in Aarey, only bushes and branches trimmed: MMRCL to SC

No tree cutting in Aarey, only bushes and branches trimmed: MMRCL to SC

Solicitor General Tushar Mehta, appearing for MMRCL, told a bench headed by Justice U U Lalit that he had made a statement before the apex court in 2019 that no further cutting of trees will be done for a metro car shed in Aarey colony and after that, no trees have been cut there

05 August,2022 03:16 PM IST | New Delhi | mid-day online correspondent